During the fall 2014 Uniteam finalized the installation and delivery of qty 3 blast and fire protected 50 man SIPs in Aksai, Kazakhstan for KPO.
The SIP structure was made by Uniteam in Poland, outfitted and finalized by complete FAT at Uniteam in Oslo, Norway, before sending the complete solution to Aksai, Kazakhstan.
The SIPs with SIL 3 F&G system, HVAC and breathing air bottle bank system gives personnel at site protection for the dangerous H2S gas in the area for 2 hours, and are the most complex SIPs delivered by Uniteam so far. The SIPs are overpressurized and give protection against all external gases or smoke.
Uniteam Site Manager as well as the Client were exceptionally satisfied with the final result and the effective deployment of all 3 SIPs at site. Project shows that well prepared FAT in Norway will reduce time during deployment/commissioning at site to minimum.